NIGERIA: Decklar Resources Continues Re-entry Operations at the Oza-1 Well Site
Re-entry operations at the Oza-1 well site continue to progress with the completion of critical initial work activities including pulling the existing tubing and the 5 ½ inch casing that was inside the 9 ⅝ inch casing.
The 9 ⅝ inch casing has been scrapped and circulated clean and over to brine completion fluid and a cement bond log has been run to confirm the integrity of the wellbore and cement behind the casing.
Cased hole reservoir logs have been completed and analyzed and confirm the expected characteristics of the zones targeted for testing. Surface testing facilities and equipment are currently being installed, and it is anticipated that testing of the L2.6 zone will commence early next week.
Perforation operations will begin with a testing tubing string run with straddle packers to enable testing of the three isolated individual zones that will be tested.
Production testing operations are planned for the three known oil-bearing zones (L2.2, L2.4 and L2.6), and each targeted zone will be production flow tested independently. All test volumes produced will be exported and sold through the existing production facilities and pipelines.
Once testing of all three zones is completed, it is anticipated that a final dual-tubing string completion will be installed, and two of the three zones tested will be placed into production based upon successful testing. All necessary approvals and permits are in place for the well re-entry, testing and completion.
As previously announced, once the Oza-1 re-entry is complete, the drilling rig is then expected to be skidded on the same drill pad as the Oza-1 well to a new drilling slot and a horizontal development well will be drilled in one of the three zones tested in the Oza-1 well. It is anticipated that this well will then be placed on production upon successful testing and completion.
The Oza-1 well and new horizontal development well are expected to generate significant production levels and generate cash flow in a short time frame utilizing the existing infrastructure in place. The Oza Oil Field development is planned to then continue with one or two more re-entries on other existing wells and an additional development drilling program with a potential for eight to ten wells to be drilled to achieve full-field development. Additional early production and central processing facilities will be added as required to accommodate increased production levels from field development activities.
The Company anticipates that operations are on track for initial production testing to commence immediately following perforating and running the testing string. The Oza Oil Field has significant export and production capacity through processing facilities and infrastructure already in place and operational, which will allow for the immediate export and sale of crude oil from the Oza-1 well.
Decklar also continues to pursue and advance evaluations and negotiations for additional proven undeveloped oil and gas fields in Nigeria that have significant reserves and near-term production potential, including the recently announced acquisition in the Asaramatoru oil field.